Filters
Question type

Study Flashcards

Prepare a budget for manufacturing costs for Nacelle Manufacturing for the month of July 2016 from the following information.Direct materials are estimated to be $480,000 for the year and direct labor is estimated to be $96,000.The direct labor per hour average is $13 and the budgeted level of activity for the month is 1,200 hours. Prepare a budget for manufacturing costs for Nacelle Manufacturing for the month of July 2016 from the following information.Direct materials are estimated to be $480,000 for the year and direct labor is estimated to be $96,000.The direct labor per hour average is $13 and the budgeted level of activity for the month is 1,200 hours.

Correct Answer

verifed

verified

To measure manufacturing efficiency,it is necessary to first identify cost behavior and separate cost into their components.

A) True
B) False

Correct Answer

verifed

verified

Material budgets are computed by multiplying units to be produced by the unit cost of direct materials.

A) True
B) False

Correct Answer

verifed

verified

The labor standard for a product was five hours at a wage rate of $8 per hour.The firm produced 900 units of the item.Labor costs totaled $35,250 and 4,700 hours of labor were used.An analysis of labor costs would indicate


A) a $750 favorable labor time variance.
B) a $1,600 favorable labor time variance.
C) a $2,350 unfavorable labor rate variance.
D) a $2,350 favorable labor rate variance.

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The Costmore Company uses standard costing and has established the following standards for direct materials and direct labor for each unit it makes: The Costmore Company uses standard costing and has established the following standards for direct materials and direct labor for each unit it makes:   During July,the company made 4,000 units of product and used 13,000 gallons.The actual price paid for materials was $5.20 per gallon. Direct Labor used was 3,600 hours and workers were paid $11.75 per hour. An analysis would indicate A)  a $900 unfavorable labor efficiency variance. B)  a $900 favorable labor efficiency variance. C)  a $4,800 unfavorable labor efficiency variance. D)  a $4,800 favorable labor efficiency variance. During July,the company made 4,000 units of product and used 13,000 gallons.The actual price paid for materials was $5.20 per gallon. Direct Labor used was 3,600 hours and workers were paid $11.75 per hour. An analysis would indicate


A) a $900 unfavorable labor efficiency variance.
B) a $900 favorable labor efficiency variance.
C) a $4,800 unfavorable labor efficiency variance.
D) a $4,800 favorable labor efficiency variance.

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

The quantity variance for an item is the difference between its actual quantity and its standard quantity multiplied by


A) the standard cost of the item.
B) the actual cost of the item.
C) the price variance.
D) the budgeted amount for the item.

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

A flexible budget shows budgeted costs at several different levels of activity.

A) True
B) False

Correct Answer

verifed

verified

Petersen Company produces a single product with the following production and average cost data: Petersen Company produces a single product with the following production and average cost data:   The best estimate of total cost at an activity level of 7,250 units is: A)  $424,500 B)  $433,250 C)  $439,500 D)  $458,250 The best estimate of total cost at an activity level of 7,250 units is:


A) $424,500
B) $433,250
C) $439,500
D) $458,250

E) A) and D)
F) None of the above

Correct Answer

verifed

verified

The ____________________ cost per unit does not change as output changes.

Correct Answer

verifed

verified

Which variance is controllable by the production manager?


A) standard overhead variance.
B) labor rate variance.
C) labor usage variance.
D) material price variance.

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The cost per unit of direct materials changes as output changes.

A) True
B) False

Correct Answer

verifed

verified

One element that is NOT part of the standard cost is


A) shipping.
B) labor.
C) materials.
D) machine maintenance.

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

  Complete the Budget Performance Report for Soville Manufacturing using the information given.Comment on the results. Complete the Budget Performance Report for Soville Manufacturing using the information given.Comment on the results.

Correct Answer

verifed

verified

Usually,a well-run manufacturing company prepares only annual manufacturing cost budgets.

A) True
B) False

Correct Answer

verifed

verified

A simple method used to analyze the fixed and variable components in semi-variable costs is called the ____________________ point method.

Correct Answer

verifed

verified

  Use the high-low point method to determine total fixed cost: A)  $20,000. B)  $28,000. C)  $16,000. D)  $24,000. Use the high-low point method to determine total fixed cost:


A) $20,000.
B) $28,000.
C) $16,000.
D) $24,000.

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

The labor standard for a product was five hours at a wage rate of $8 per hour.The firm produced 900 units of the item.Labor costs totaled $35,250 and 4,700 hours of labor were used.An analysis of labor costs would indicate


A) a $750 favorable labor time variance.
B) a $1,600 unfavorable labor time variance.
C) a $750 unfavorable labor rate variance.
D) a $1,600 favorable labor rate variance.

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Explain the process for establishing standard costs for manufactured products.Identify the parties responsible and accountable for the standard.

Correct Answer

verifed

verified

Establishing standard costs for manufact...

View Answer

Semi-variable costs are sometimes called mixed costs.

A) True
B) False

Correct Answer

verifed

verified

Deducting the total variable cost from the total cost results in the


A) overhead.
B) fixed cost.
C) manufacturing cost.
D) semivariable cost.

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

Showing 81 - 100 of 118

Related Exams

Show Answer