When specific work packages are assigned to a particular group or person within the organization, the result is called a(n) ___________.


A) work breakdown structure
B) process breakdown structure
C) organization breakdown structure
D) project priority matrix
E) responsibility matrix

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

A "Dissemination Mode" is


A) how project schedules are version controlled.
B) a description of what is important to project stakeholders.
C) what defines how project communication is to occur.
D) None of these choices are correct.
E) All of these choices are correct.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

A Responsibility Matrix will clarify


A) tasks.
B) supports.
C) responsibilities.
D) who supports and who is responsible.
E) All of these alternatives are correct.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Creating a communication plan typically follows a process that begins with a stakeholder analysis.

A) True
B) False

Correct Answer

verifed

verified

What is a work package and what information does it contain?

Correct Answer

verifed

verified

A work package is the lowest element in ...

View Answer

In terms of project management, what is a deliverable? Give an example.

Correct Answer

verifed

verified

A deliverable is an expected o...

View Answer

The type of information that will need to be collected during a project and who will receive this information can be found in the project __________ plan.


A) communication
B) requirements
C) responsibility
D) assignment
E) creation and design

F) A) and D)
G) D) and E)

Correct Answer

verifed

verified

In many cases, the causes of scope creep reflect a misfit between ____.


A) traditional project management methods being applied to high uncertainty projects
B) agile project management methods being applied to projects with stable, static scope
C) traditional project management methods being applied to projects with high certainty
D) agile project management methods being applied to projects with high predictability
E) agile project management methods being applied to projects involving the application of uncertain technology

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

Identify and briefly describe the eight elements on the recommended project scope checklist.

Correct Answer

verifed

verified

Acceptance...

View Answer

The use of "acceptance criteria" only refers to projects with external customers who are paying for the project.

A) True
B) False

Correct Answer

verifed

verified

How would you mark Time, Performance and Cost on a Project Priority Matrix if you wanted to be first to market with your product to garner market share. You are willing to defer original scope requirements to later versions in order to get to the market first. Going over budget is acceptable but not desirable. Fill out the Project Priority Matrix below:

Correct Answer

verifed

verified

The correct answer is the following:
blured image T...

View Answer

Which of the following items on the Project Scope Checklist answers the question "What is the problem or opportunity the project is addressing?"


A) Project objective
B) Product scope description
C) Justification
D) Deliverables
E) Milestones

F) A) and D)
G) B) and C)